NYC Highways : Forewarned is Forearmed


Please see below the details of the utility improvement schemes scheduled for delivery on Harrogate’s highway network in 2026. As always, dates and timescales are subject to change depending on the individual projects.

The list below shows that Harrogate continues to experience significant demand on its highway network. The Highways team remains in regular communication with utility project leads and, by working closely with the communications representatives for each scheme, aims to support improved collaboration and ensure consistent messaging and updates for Harrogate residents.

Updates will continue to be provided throughout the year (the next update is planned for March/April). In the meantime, if site‑specific information is required, this can be found at: Causeway one.network.

Killinghall

Northern Gas Networks – replacement scheme (2026)

  • Grainbeck Lane 22nd June – 14th August Road closure

  • Grainbeck Lane junction with Otley Road 7th April – 8th July Multiway signals

  • Church Close 20th April – 1st May Some carriageway incursion

  • Manor Road 27th April – 8th May Some carriageway incursion

  • Otley Rd, Killinghall : April – Aug, 14 weeks

Northern Powergrid – disconnection of lighting columns (2026)

  • Otley Road 6th – 19th January two way signals

Northern Gas Networksremedial works on high pressure main (2026)

  • Skipton Road 3rd August – 7th September Multiway signals – various meeting held during Tesco S278 works to see if collaborative working was feasible but unfortunately it was not.

West of Harrogate

Harrogate Spring Water, (Section 50 works) (2026)–7 day working and manually controlling the lights 7am to 7pm daily

  • Oaker Bank 20th January – 1st March rolling two-way lights and change to Multiway lights at the roundabout

  • Penny Pot Lane 23rd February – 31st May multiway lights at the roundabout and then reduced to two-way rolling lights. (This duration may be reduced significantly as they are trying to install a large section of pipe work in private land)

  • Cornwall Road 1st June – 3rd July two-way lights

  • Harlow Moor Road 29th June – 7th August two-way lights

BT – cabling works (2026)

  • Otley Road 26th – 28th January Multiway signals to enable cabling works. Out of hours working (21:00 – 06:00) to reduce impact on the diversion route for Otley Road Northern Powergrid.

Yorkshire Water – new connection (2026)

  • Otley Road 7th – 10th April Multiway signals manned 7am to 7pm.

Yorkshire WaterHarrogate Growth Scheme

  • Beckwith Head Road junction of Otley Road 1st July to 07th August Lane Closure

  • Spring Lane 31st March – 02nd April Multiway signals

  • Church Lane 30th March -  22nd April two way signals

  • Fulwith Mill Lane 30th March – 2nd April two way signals

  • Fulwith Mill Lane 13th November – 27th November two way signals

  • Hill top lane 21st April – 23rd April two way lights

  • Whinney Lane, Lady Lane, Hill Top Lane 13th May – 1st July Multi way signals

  • Lady lane 2nd July – 13th November Road Closure

  • Lady Lane junction Beckwith Head Road 16th November – 07th November multi way signals

  • Hill top lane 9th February – 11th March two way signals

  • Church Lane 25th July – 30th July two way signals

  • Church Lane 27th October – 3rd November multiway signals

  • Church Lane 1st May – 11th May two- way signals

  • Church Lane 24th – 29th September two way signals

  • Beckwith Head Road 10th December 2026 to 8th February 2027 two way signals

Harrogate

Yorkshire Water renewal of water mains schemes (2026)

  • Duchy Road 24th November – 25th January (Cleared for Christmas shut down) Two-way lights

  • Hereford Road 19th January – 13th February Multiway signals

  • Duchy Road 16th March – 22nd April Multiway signals. Northern Powergrid need to work at this location, so discussion is taking place to see if collaborative working is feasible.

  • York Road 26th January – 13th March Multiway signals

Yorkshire Water – Emergency burst water main (2026)

  • Cornwall Road 9th January – 15th January 

Northern Powergrid – Balfour Beatty 33Kv and 11Kv Major scheme
(2025/2026) 33 individual joint bays, 10metres in lengths, 16 11KV joint bays.

To be complete by July 2026

  • Ripon Road 20/3 – 26/3 temporary lights Northern Powergird, Balfour Beatty

  • Ripon Road 31/3 – 22/5 temporary lights Northern Powergird, Balfour Beatty

  • Coppice Drive 18/3 – 8/4 Road Closure Northern Powergrid, Balfour Beatty

  • Ripon Road 17/3 – 25/3 temporary lights Northern Powergrid, Balfour Beatty

  • Ripon Road 30/3 – 23/4 temporary lights Northern Powergrid, Balfour Beatty

  • Jenny Field Drive 8/4 – 4/6 multi way signals Northern Powergird, Balfour Beatty

  • Jenny Field Drive 2/4 – 6/5 Two way signals Northern Powergrid, Balfour Beatty

  • Crescent Garden 5/1 -14/1 Multi way signals Northern Powergird, Balfour Beatty

  • Valley Drive 19/3 – 29/4 Two way signals Northern Powergrid, Balfour Beatty

  • Queens Road 17/2 – 25/2 two way signals Northern Powergird, Balfour Beatty

  • Queen Road 9/3 -7/4 two way signals Northern Powergird, Balfour Beatty

  •  Leeds Road 3/3 – 17/3 temporary lights Northern Powergird, Balfour Beatty

  • Leeds Road 27/2 – 11/3 temporary lights Northern Powergird, Balfour Beatty

  • Otley Road 5/1 – 15/2 Road Closure Northern Powergrid, Balfour Beatty

  • Knaresborough Road 25/2 -7/3 Two way signals Northern Powergird, Balfour Beatty

  • Knaresborough Road 23/2 – 5/3 Two way signals Northern Powergird, Balfour Beatty

  • Knaresborough Road 3/2 -13/2 two way signals Northern Powergrid, Balfour Beatty

  • York Place 5/2 – 19/2 Lane Closure Northern Powergrid, Balfour Beatty

  • Leeds Road, York Place 19/1 -22/1 Multiway signals NPG, Balfour Beatty (Prince of Wales roundabout)

  • Prospect Road 5/5 – 19/6 Road Closure Northern Powergird, Balfour Beatty

Northern Powergrid –New connection

  • Swan Road 5/1 – 8/2 Road Closure Northern Powergird

  • Crescent Road 7/4 – 28/4 Contraflow Northern Powergird

  • Parliament Street 16/3 – 26/4 Lane Closure Northern Powergird

  • Hospital scheme – Lancaster Park Road dates unknown at present

  • Cold Bath Road - 220 metres Date to be confirmed

Northern Gas Networks – replacement schemes (2026)

  • Forest Lane 7th April – end of May rolling two way lights

  • Starbeck, 200m replacement end of April. Railway line to Knaresborough. Temporary lights.

  • Hampsthwaite Road, Harrogate : Sep – Feb 27, 20 weeks

  • Yew Tree Gardens, Harrogate : Jul – Oct, 15 weeks

  • High Street, Knaresborough : Jul – Sep, 8 weeks

Knaresborough

 Yorkshire Water – 2026 Continuation to the scheme they commenced 2025

  • York Road 12/2 – 20/2 Multiway signals Yorkshire Water

  •  Chain Lane 9/2 – 15/2 Multiway signals Yorkshire Water

Harrogate Capital Highways schemes

Highway planned maintennace schemes will be delivered at the following locations in 2026/27:

Harrogate

Carriageway Patching

  • St Andrews Avenue

  • St Andrews Walk

  • St Andrews Parade

  • St Andrews Place

  • St Andrews Grove

  • St Andrews Street

  • St Andrews Road

  • St Andrews Crescent

  • Cawthorn Avenue

  • Wedderburn Road

  • Wedderburn Drive

  • Tyson Place

  • Fairfax Avenue

  • Stonefall Drive

  • Stonefall Place

  • St Nicholas Road

  • St Patricks Way

R&R ( Resurfacing)

  • Ripon Way

  • Oakdale Avenue

  • Kingsley Close

Footway R&R (Resurfacing)

  • Raglan Street

Footway Patching

  • Chaucer Green

  • Knox Close

  • Harlow Pines

  • Manor Road

Footway Slurry Seal

  • Park House Green

  • Knox Chase

  • Knox Rise

  • Knox Way

  • Knox Drive

  • Knox Grove

  • St Johns Way

  • St Johns Grove

  • St Johns Drive

  • Westville Oval 

Surface Dressing

  • Willaston Road

  • Silverfields Road Rear

  • Roseville Road

  • Roseville Drive

  • Anchor Road

  • Road Rear Of Torrs Road

  • Torrs Road

  • Lynton Gardens

  • Road Rear Of Hurstleigh Terrace

  • Hurstleigh Terrace

  • Bramham Drive

  • Burnby Close

  • Markenfield Road

  • Beningbrough Drive

  • Nunnington Crescent

Skipton Road To Devonshire Place

  • Devonshire Place

  • County Parade

  • County Square

  • Claro Avenue

  • Hambleton Road

  • Ainsty Road

  • Gascoigne Crescent

  • Avondale Road

  • Slingsby Crescent

  • Skipton Road To Granby Road

  • Granby Road

  • Highgate Park

  • Silverfields Road

  • Roseville Avenue

  • Harewood Road


← BACK TO BUSINESS HUB
Previous
Previous

Leading Regional Lawyer Boosts Berwins’ Private Client Practice

Next
Next

Snow Is Falling All Around Me: Do I Really Have To Go To Work?