North Yorkshire Highways : Harrogate Update
The Northern Powergrid, Balfour Beatty 33KV scheme continues
Cold Bath Road 25/5 currently the end date is showing incorrectly on One.Network and I can confirm that they are planning on carrying out the work during the school half term holiday, completing on 30/5. This will be a road closure with signed diversions in place.
Queens Road 4 – 29/6 Road closure
Otley Road, Harrogate 14/7 – 15/8 Road closure
Trinity Road 18 – 29/6 Road closure
Leeds Road 13/5 – 22/6 Multiway signals
Beech Avenue 12 – 25/5 Multiway signals
Otley Road 11 – 17/8 Multiway signals
York Place 11 – 17/8 Multiway signals
Knaresborough Road 14/8 – 9/9 Multiway signals
High Street 29/6 – 12/7 Multiway signals
Prospect Road 25/6 – 4/7 Road Closure
The Northern Powergrid, O’Connors 11kv scheme continues
Chudleigh Road 19 – 23/5 Road closure
East Parade 22/5 – 2/6 Two way signals
Dragon Parade 5 – 17/6 Multiway signals
Bower Road 2 – 6/6 Road Closure
Dragon Road 5 – 17/6 Multiway signals
Skipton Road 6 – 18/5 Multiway signals
Skipton Road 27/5 – 2/6 Multiway signals
Grove Road 8/4 – 20/5 Multiway signals
17th March to Mid-July- Victoria Avenue Active Travel Fund – North Yorkshire County Council Highway works
The scheme aims to improve the public realm and pedestrian provision on Victoria Avenue by:
Adding signalised pedestrian crossings to Victoria Avenue at the Station Parade and West Park Junctions and upgrades of existing traffic signals to bring up to modern standards
Adding tactile paving to side roads
a new bus stop located outside the United Reformed Church and upgrading the paving between West Park and Princess Square
Improvements to existing paving where issues have been identified
Replacing paving across accesses to indicate pedestrian priority
New decorative footway lighting
New bins and benches to match the future Station Gateway scheme
Relocated ticket machines to suit new layout
Layout improvements to help prevent vehicles from making the illegal straight-ahead movement from Beech Grove to Victoria Avenue
Works are progressing well and in accordance with the accepted programme. Works at the junction of Station Parade and Victoria Avenue will be completed at the end of this month. By the end of the month the contractors should also have completed the improvements to the Belford Avenue/Victoria Avenue Zebra crossing along with the paving upgrades between Station Parade and Belford Avenue.